Spen Valley Leisure Centre – progress on site

As our project Spen Valley Leisure Centre enters it’s final phase of works, the following progress is taking place on site:

  • The project is well in to its final phase of finishes and final fix M&E
  • The gym exercise studio floor has been installed along with a raised floor in the gym
  • The first floor changing room cubicle fit-out has been completed
  • Ceramic tiling has been completed to the changing rooms with the pool surrounds programmed to commence following the completion of the high level works
  • The new substation has been installed and the old one now demolished allowing testing and commissioning to start in the building
  • The external works have recommenced with preparation for street furniture/block paving, tarmac and landscaping ongoing
Previous Post

Shakespeare North - progress on site

This month has seen two major events happen at our ... Read more

Next Post

North West Regional Construction Awards 2021

We are delighted to confirm that we have been shortlisted ... Read more