Our project, Citizens Theatre in Glasgow continues to make good progress and works taking place on site at present are:
- Stripping of old roofs, installation of new sarking and thereafter reinstatement of the original roof slate
- Stone masonry repairs and re-pointing is underway
- Replacing historic window arches and cills has begun
- Challenging temporary works to reshape new access and egress routes
- The new extension concrete floors are almost complete, as is the installation of the new modern flat roofs
- The new brick facade & SFS wall linings are coordinating well with fire protection to the steel nearing completion.
- The internal strip out is progressing well to the existing building, with the services first fix started.
- Statues are waiting patiently for their elevation next year
There is a blog available on the project and you can read more about it here.
Previous Post
Shakespeare North Playhouse hosts Open Doors Week launch event
Our Shakespeare North project has hosted the Open Doors Week ... Read more
Next Post
Anthony Frith - Coast to Coast Challenge
Anthony Frith (Site Manager in our Nottingham business) undertook the ... Read more