Darley Street Markets – progress on site

Our project, Darley Street Markets in Bradford is progressing well and we are in week 20 of 113.

The plot is divided into two sections – on the right hand side of the top left photo below is the old Marks & Spencer building and on the left hand side is the old Woolworths building. Demolition works are well underway and works are progressing safely. We are targeting the demolition works being substantially complete by the end of the year when the main building works will begin.

We have a time-lapse camera on the project and you can view the most recent video here. Our Client has also taken some drone progress photos and these are below:

Previous Post

St Albans Place - RIBA Yorkshire - Building of the Year Award

We are delighted to confirm that our project, St Albans ... Read more

Next Post

“Our drive to transform the industry creates opportunities for new roles and skills in the industry.”