On the 13th September we handed over the completed basement which houses the sixth forms dining area and kitchen at Dixons Academy in Bradford to a delighted Client.
This follows on from the recent completion of the ground and first floor and the College is now fully operational to students and teachers.
The reminder of the works to the second, third and fourth floors, the sports hall and coach house will continue until March 2020.
The most recent milestone on the project is the completion of the steel frame for the sports hall.