Progress at Bishop Barrington School

Our project at Bishop Barrington School is progressing well and we are currently working on phase 2 of the project to complete the external landscaping works. The new teaching block, that was phase 1 of the project, was handed over back in August 2020.

Current progress on site includes:

  • Demolition of the old school has been completed in April, 3 weeks ahead of programme
  • Groundworks to the permeable car park areas, roadworks and attenuation tank and drainage is all complete with kerb-lines and block paving now ongoing
  • Area 1 of the external works was handed over early to the Client on 9th April

The project is currently on target for completion in the autumn of 2021.